Weil-McLain · Boiler · Startup

Startup procedure

SlimFit Series 2

What happens, in order

  1. Turn the boiler ON/OFF switch off.
  2. Read and follow the operating instructions on page 85 (Figure 78).
  3. Turn the boiler on. The control initialises and follows its normal sequence of operation.
  4. Check flame and combustion with instruments at high fire.
  5. Run the boiler for 10 minutes before measuring gas input.
  6. Measure natural gas input and compare against the rating label.
  7. Check low fire flame stability in Manual test mode.
  8. Set the firing rate back to AUTO when testing is complete.
  9. Complete the verification checklist before leaving the boiler.

Timings and thresholds

ItemValue
Burn-in before gas input measurement10 minutes

Codes you may see during this

Ignition Fault

Applies to: SlimFit Series 2 startup

Models

SF1000SF1500SF2000

More Weil-McLain boiler sequences

Take it to the job

Sequences of operation, error codes and tips work offline in the HVACopedia app.

Open the app

Source: SlimFit Series 2 boiler manual 550-100-561/1225, p. 82-84. Written in our own words; timings can differ by model and software version, so check the manual for your exact unit.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.