Weil-McLain · Boiler · Startup
Closure switch interlock startup sequence
What happens, in order
- A call for heat closes an input contact.
- The corresponding output energizes, which may move the damper or shared device.
- The blower stays off until the closure switch makes.
- If the switch opens before ignition, the timer continues and the blower stays active.
- If the switch does not make within the allowed time, the control locks out.
- If the switch opens during burner firing, the control locks out.
- The output remains energized while the control tries to close the switch.
Timings and thresholds
| Item | Value |
|---|---|
| Closure switch allowed time | 4 minutes |
Applies to: Flow switch or CAD interlock
Models
SVF 1500SVF 2000SVF 2500SVF 3000
More Weil-McLain boiler sequences
- Annual start-up checklist (service technician) · Startup
- Blower calibration at first startup · Startup
- Check flame and combustion with instruments · Startup
- Check flame and combustion with instruments at high fire, low fire and auto · Startup
- Express Setup Example B wizard order (Combi with two zones) · Startup
- Final verification checklist at commissioning · Startup
- Lighting and operating sequence · Startup
- Power-up and ignition sequence · Startup
Take it to the job
Sequences of operation, error codes and tips work offline in the HVACopedia app.
Source: SVF Series 1 boiler manual, pp. 62-63. Written in our own words; timings can differ by model and software version, so check the manual for your exact unit.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.