Weil-McLain · Boiler · Startup
Final verification checklist at commissioning
What happens, in order
- Confirm the boiler and heat distribution units are filled with water.
- Confirm any automatic air vent is open one full turn and air is purged from the system.
- Purge air from the gas piping and check the piping for leaks.
- Confirm the correctly sized manifold orifices are installed (Table 5, page 17).
- Follow the operating instructions and confirm a proper burner flame (see Check Burner Flames on page 60).
- Test the temperature limit. Burners should go off while the circulator runs and restart after the setting is raised above water temperature.
- Test the low water cutoff (LWCO). Burners should go off, the circulator should keep running, and LWCO should display.
- Test any field-installed low water cutoff, high limit or other controls. Burners should go off and restart when the controls are restored.
- Test the ignition system safety device by shutting off the gas at the manual main shutoff with the burners on.
- Set the Boiler Temp adjustment to the system requirement and adjust balancing valves and controls to deliver design temperature.
- Set Economy mode.
- On multiple zones, adjust flow so it is about equal in each zone.
- Cycle the boiler with the thermostat from highest to lowest setting and confirm normal start-up and shutdown.
- Cycle the DHW aquastat if used.
- Measure natural gas input.
- Check manifold gas pressure (3.5 in. w.c. for natural gas).
- Observe several operating cycles for proper operation.
- Set the room thermostat to the desired temperature.
- Complete the Installation and Service Certificate.
- Review the instructions with the owner or maintenance person and leave them with the owner.
Timings and thresholds
| Item | Value |
|---|---|
| Run boiler before measuring gas input | 10 minutes |
Applies to: EG and PEG Series 7 boilers at commissioning
More Weil-McLain boiler sequences
- Annual start-up checklist (service technician) · Startup
- Blower calibration at first startup · Startup
- Check flame and combustion with instruments · Startup
- Check flame and combustion with instruments at high fire, low fire and auto · Startup
- Closure switch interlock startup sequence · Startup
- Express Setup Example B wizard order (Combi with two zones) · Startup
- Lighting and operating sequence · Startup
- Power-up and ignition sequence · Startup
Take it to the job
Sequences of operation, error codes and tips work offline in the HVACopedia app.
Source: Weil-McLain EG/PEG Series 7 Boiler Manual, p. 65. Written in our own words; timings can differ by model and software version, so check the manual for your exact unit.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.