Venturi screw and gas valve torque sequence in conversion

ECO Tec Series 3

What happens, in order

  1. Install the new venturi with O-ring seated.
  2. Tighten the three Torx screws to no more than 23 inch-pounds.
  3. Install the propane orifice in the venturi gas inlet.
  4. Tighten the swivel nut with two wrenches on the gas pipe.

Timings and thresholds

ItemValue
Venturi Torx screw torque (max)23 inch-pounds

Applies to: Gas conversion

Models

80110150199

More Weil-McLain boiler sequences

Take it to the job

Sequences of operation, error codes and tips work offline in the HVACopedia app.

Open the app

Source: ECO Tec Series 3 Boiler Manual, p. 21. Written in our own words; timings can differ by model and software version, so check the manual for your exact unit.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.