Uncrate and place the boiler

SVF 500/600 Series 1

What happens, in order

  1. Move the crate to a solid, level surface with room for the ramp and final placement.
  2. Place the ramp end into the pallet notch and secure it to the pallet.
  3. Remove the board marked REMOVE TO UNLOAD.
  4. Remove the eight screws and eight lag bolts from the four shipping brackets.
  5. Roll the boiler down the ramp onto a solid, level surface. Apply pressure only at the jacket corner posts or water manifolds.
  6. Keep the boiler straight while rolling. The front casters swivel and the back casters are fixed.
  7. Lower the leveling legs until they contact the floor, then remove jacket panels as needed to reach the bolts.
  8. Adjust legs until the base is 1/16 in (1.6 mm) above the floor and the boiler is level front-to-back and side-to-side on the cover plate.

Applies to: SVF 500/600 boilers

Models

SVF 500SVF 600

More Weil-McLain boiler sequences

Take it to the job

Sequences of operation, error codes and tips work offline in the HVACopedia app.

Open the app

Source: SVF 500/600 Series 1 boiler manual, p. 14-15. Written in our own words; timings can differ by model and software version, so check the manual for your exact unit.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.