What happens, in order
- Apply power to the boiler at the service switch.
- Follow the operating instructions on page 97.
- On first power-up, complete the control setup Wizard (recommended for all boilers).
- Confirm all connected sensors are detected and the correct boiler model is identified. If not, find the cause and correct it before continuing.
- Recheck water, vent, air and gas piping for leaks. If a leak is found, shut down and repair immediately.
Applies to: SVF 500/600 Series 1 boilers
Models
SVF 500/600
More Weil-McLain boiler sequences
- Annual start-up checklist (service technician) · Startup
- Blower calibration at first startup · Startup
- Check flame and combustion with instruments · Startup
- Check flame and combustion with instruments at high fire, low fire and auto · Startup
- Closure switch (flow switch or CAD) proof sequence · Startup
- Closure switch interlock startup sequence · Startup
- Express Setup Example B wizard order (Combi with two zones) · Startup
- Final verification checklist · Startup
Take it to the job
Sequences of operation, error codes and tips work offline in the HVACopedia app.
Source: SVF 500/600 Series 1 Boiler Manual, p. 98. Written in our own words; timings can differ by model and software version, so check the manual for your exact unit.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.