Weil-McLain · Boiler · Heating
Space heating and DHW operation
What happens, in order
- When flame is detected, the boiler is released to modulation. Blower speed and gas flow change to match demand.
- If flame is not detected, the gas valve closes, the blower runs postpurge, and the cycle restarts.
- When a priority timer ends, control switches to the next priority and starts its timer.
- When demand is satisfied (target reached or limit), go to postpurge.
Applies to: SlimFit 1000-2000 Series 2 boilers
More Weil-McLain boiler sequences
- Annual start-up checklist (service technician) · Startup
- Blower calibration at first startup · Startup
- Check flame and combustion with instruments · Startup
- Check flame and combustion with instruments at high fire, low fire and auto · Startup
- Closure switch (flow switch or CAD) proof sequence · Startup
- Closure switch interlock startup sequence · Startup
- Express Setup Example B wizard order (Combi with two zones) · Startup
- Final verification checklist · Startup
Take it to the job
Sequences of operation, error codes and tips work offline in the HVACopedia app.
Source: SlimFit Series 2 Boiler Manual 550-100-561/1225, p. 62. Written in our own words; timings can differ by model and software version, so check the manual for your exact unit.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.