Weil-McLain · Boiler · Startup
Pre-start checks and first start
What happens, in order
- Do not run the boiler unless it and the system are full of water and all previous procedures are complete.
- Read the Operation section, the operating instruction for the matching gas valve, and check the water fill and the start-up preparation steps.
- Check system piping for leaks and repair any leak found.
- Vent air from the system using the manual vents.
- Inspect the vent system for corrosion, damage, or sagging, and confirm masonry chimney liners are sound with no obstructions or openings.
- Check around the boiler for gas odor.
- Verify operation and complete the final verification checklist, then fill in the installation and service certificate.
Applies to: CGi-25 to CGi-8
Models
CGi-25 to CGi-8
More Weil-McLain boiler sequences
- Annual start-up checklist (service technician) · Startup
- Blower calibration at first startup · Startup
- Check flame and combustion with instruments · Startup
- Check flame and combustion with instruments at high fire, low fire and auto · Startup
- Closure switch (flow switch or CAD) proof sequence · Startup
- Closure switch interlock startup sequence · Startup
- Express Setup Example B wizard order (Combi with two zones) · Startup
- Final verification checklist · Startup
Take it to the job
Sequences of operation, error codes and tips work offline in the HVACopedia app.
Source: CGi Series 5 boiler manual, p. 63 and 64. Written in our own words; timings can differ by model and software version, so check the manual for your exact unit.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.