  1. Do not run the boiler unless it and the system are full of water and all previous procedures are complete.
  2. Read the Operation section, the operating instruction for the matching gas valve, and check the water fill and the start-up preparation steps.
  3. Check system piping for leaks and repair any leak found.
  4. Vent air from the system using the manual vents.
  5. Inspect the vent system for corrosion, damage, or sagging, and confirm masonry chimney liners are sound with no obstructions or openings.
  6. Check around the boiler for gas odor.
  7. Verify operation and complete the final verification checklist, then fill in the installation and service certificate.

Applies to: CGi-25 to CGi-8

Models

CGi-25 to CGi-8

More Weil-McLain boiler sequences

Take it to the job

Sequences of operation, error codes and tips work offline in the HVACopedia app.

Open the app

Source: CGi Series 5 boiler manual, p. 63 and 64. Written in our own words; timings can differ by model and software version, so check the manual for your exact unit.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.