Weil-McLain · Boiler · Other
Installation sequence - direct vent vertical concentric
What happens, in order
- Read this manual and pages 25 through 28 before starting vent/air work.
- Install the boiler where all vent and air piping can route to the termination location.
- Confirm the vertical termination location meets the clearances in the manual figure and multi-boiler spacing figure.
- Use only listed vent materials and add pipe adapters where required.
- Check that total vent and air lengths do not exceed the allowed maximum.
- Assemble and install the concentric termination before connecting piping from the boiler.
- Prepare the vertical penetration, assemble the kit and secure penetration components with supports.
- Install vent and air piping to the termination, sloping horizontal runs down toward the boiler at least 1/4 in per foot.
- Install pipe supports every 5 ft on horizontal and vertical runs.
- Install a hanger support within 6 in of any upturn in the piping.
- Use sweep elbows only. Do not use short radius elbows in vent or air piping.
Timings and thresholds
| Item | Value |
|---|---|
| Horizontal pipe slope | 1/4 in per foot down toward boiler |
| Pipe support spacing | max 5 ft apart, horizontal and vertical |
| Hanger support from upturn | within 6 in |
Applies to: Vertical concentric direct vent
Models
80/110/150/199 Series 3
More Weil-McLain boiler sequences
- Annual start-up checklist (service technician) · Startup
- Blower calibration at first startup · Startup
- Check flame and combustion with instruments · Startup
- Check flame and combustion with instruments at high fire, low fire and auto · Startup
- Closure switch interlock startup sequence · Startup
- Express Setup Example B wizard order (Combi with two zones) · Startup
- Final verification checklist at commissioning · Startup
- Lighting and operating sequence · Startup
Take it to the job
Sequences of operation, error codes and tips work offline in the HVACopedia app.
Source: ECO Tec Series 3 Boiler Manual, p. 41. Written in our own words; timings can differ by model and software version, so check the manual for your exact unit.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.