Weil-McLain · Boiler · Heating
Heat demand to output energising
What happens, in order
- An input (Input 1 to 4) closes its dry contact to call for heat or indirect DHW.
- The control checks that the priority assigned to that input/output pair is active.
- If the priority is active, the matching 120 Vac output (Output 1 to 4) energises.
- The zone can call, but its pump does not run unless the boiler is already running on that system and priority.
- With 0-10 Vdc modulation, the boiler starts at 0.9 Vdc and stops at 0.5 Vdc, and Output 2 follows the heat demand.
Timings and thresholds
| Item | Value |
|---|---|
| Remote modulation start level | 0.9 Vdc |
| Remote modulation stop level | 0.5 Vdc |
Applies to: SVF 500/600 Series 1 boilers
More Weil-McLain boiler sequences
- Annual start-up checklist (service technician) · Startup
- Blower calibration at first startup · Startup
- Check flame and combustion with instruments · Startup
- Check flame and combustion with instruments at high fire, low fire and auto · Startup
- Closure switch (flow switch or CAD) proof sequence · Startup
- Closure switch interlock startup sequence · Startup
- Express Setup Example B wizard order (Combi with two zones) · Startup
- Final verification checklist · Startup
Take it to the job
Sequences of operation, error codes and tips work offline in the HVACopedia app.
Source: Weil-McLain SVF 500/600 Series 1 boiler manual 550-100-273/1224, pp. 72, 77. Written in our own words; timings can differ by model and software version, so check the manual for your exact unit.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.