Weil-McLain · Boiler · Heating
Flame detected and modulation, with retry logic
What happens, in order
- When flame is detected, the boiler releases to modulation for space heating or DHW.
- If the priority timer runs out, the control switches to the next priority and starts that priority's timer.
- If flame is not detected, the gas valve closes, the blower runs postpurge, and the control starts the cycle again.
- If flame is missed 5 times, the control waits 60 minutes before trying again.
Timings and thresholds
| Item | Value |
|---|---|
| Ignition retry lockout | after 5 failed ignitions, wait 60 minutes |
Applies to: Space heating and DHW heating on ECO Tec Series 3
More Weil-McLain boiler sequences
- Annual start-up checklist (service technician) · Startup
- Blower calibration at first startup · Startup
- Check flame and combustion with instruments · Startup
- Check flame and combustion with instruments at high fire, low fire and auto · Startup
- Closure switch interlock startup sequence · Startup
- Express Setup Example B wizard order (Combi with two zones) · Startup
- Final verification checklist at commissioning · Startup
- Lighting and operating sequence · Startup
Take it to the job
Sequences of operation, error codes and tips work offline in the HVACopedia app.
Source: ECO Tec Series 3 Condensing Gas Boiler Boiler Manual, p. 84. Written in our own words; timings can differ by model and software version, so check the manual for your exact unit.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.