What happens, in order

  1. Power up the control and read the startup screen.
  2. Select USE WIZARD (recommended) or SKIP WIZARD.
  3. Select the control configuration (single boiler is for stand-alone use).
  4. Confirm the boiler model (SVF 500 or SVF 600) and press ACCEPT.
  5. Set the essential boiler settings fuel type, altitude, temperature units, WWSD temp, manual reset high limit, and auto daylight savings time.
  6. Answer the ODT sensor exemption question.
  7. Start or skip blower calibration. Calls for heat are ignored until calibration is complete.

Applies to: SVF 500/600 Series 1

Models

SVF 500SVF 600

More Weil-McLain boiler sequences

Take it to the job

Sequences of operation, error codes and tips work offline in the HVACopedia app.

Open the app

Source: Weil-McLain SVF 500/600 Series 1 boiler manual, p. 88. Written in our own words; timings can differ by model and software version, so check the manual for your exact unit.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.