- Confirm the boiler and heat distribution units are filled with water and the automatic air vent is open one turn.
- Purge air from the system and gas piping, and check the gas piping for leaks.
- Confirm correct manifold orifices are installed for the fuel type (Table 4, page 16).
- Follow the operating instructions and observe a proper burner flame.
- Test the temperature limit, the low water cutoff, any field controls and the ignition safety device.
- Operate the boiler for 10 minutes with other gas appliances off, then time one cubic foot of gas at the meter in seconds.
- Calculate input 3600 x 1000 divided by the seconds counted = Btuh, and compare with the rating label.
- Check manifold pressure at the downstream tap on the main gas valve.
- Set the boiler temperature, set Economy mode, balance zones, cycle the thermostat and DHW aquastat, and complete the certificate.
Timings and thresholds
| Item | Value |
|---|---|
| Operate boiler before gas input check | 10 minutes |
| Gas input calculation | 3600 x 1000 / seconds per cubic foot |
Applies to: CGi Series 5 boilers
Models
CGi Series 5
More Weil-McLain boiler sequences
- Annual start-up checklist (service technician) · Startup
- Blower calibration at first startup · Startup
- Check flame and combustion with instruments · Startup
- Check flame and combustion with instruments at high fire, low fire and auto · Startup
- Closure switch (flow switch or CAD) proof sequence · Startup
- Closure switch interlock startup sequence · Startup
- Express Setup Example B wizard order (Combi with two zones) · Startup
- Final verification checklist · Startup
Take it to the job
Sequences of operation, error codes and tips work offline in the HVACopedia app.
Source: Weil-McLain CGi Series 5 boiler manual, p. 66. Written in our own words; timings can differ by model and software version, so check the manual for your exact unit.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.