Weil-McLain · Boiler · Startup

Final verification checklist and natural gas input check

CGi Series 5

What happens, in order

  1. Confirm the boiler and heat distribution units are filled with water and the automatic air vent is open one turn.
  2. Purge air from the system and gas piping, and check the gas piping for leaks.
  3. Confirm correct manifold orifices are installed for the fuel type (Table 4, page 16).
  4. Follow the operating instructions and observe a proper burner flame.
  5. Test the temperature limit, the low water cutoff, any field controls and the ignition safety device.
  6. Operate the boiler for 10 minutes with other gas appliances off, then time one cubic foot of gas at the meter in seconds.
  7. Calculate input 3600 x 1000 divided by the seconds counted = Btuh, and compare with the rating label.
  8. Check manifold pressure at the downstream tap on the main gas valve.
  9. Set the boiler temperature, set Economy mode, balance zones, cycle the thermostat and DHW aquastat, and complete the certificate.

Timings and thresholds

ItemValue
Operate boiler before gas input check10 minutes
Gas input calculation3600 x 1000 / seconds per cubic foot

Applies to: CGi Series 5 boilers

Models

CGi Series 5

More Weil-McLain boiler sequences

Take it to the job

Sequences of operation, error codes and tips work offline in the HVACopedia app.

Open the app

Source: Weil-McLain CGi Series 5 boiler manual, p. 66. Written in our own words; timings can differ by model and software version, so check the manual for your exact unit.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.