Weil-McLain · Boiler · Ignition
EG water boiler 30-75 pilot ignition sequence
What happens, in order
- On a call for heat from CH or DHW, the display shows OPENING DAMPER and the damper opens.
- When the damper end switch closes and stays closed for 2 seconds, the display shows PILOT IGNITION.
- If the end switch is still open after 45 seconds, the control shows DAMPER FAULT, sounds the alarm and holds for 6 minutes with the damper still energized.
- If the end switch closes during or after that 6-minute hold, the control goes straight to PILOT IGNITION.
- The control energizes the spark and pilot valve and looks for flame. When flame is seen the spark stops and the pilot is watched for 2 seconds.
- If flame stays after those 2 seconds, the control moves to steady heat.
- If flame drops out, the spark comes back on and the ignition trial continues.
- If no acceptable flame signal is seen within the 15 second pilot timer, the control cuts power, closes the damper, waits 6 minutes and retries.
- Natural gas units have no limit on pilot ignition retries.
- After a successful pilot ignition the control energizes the main gas valve.
Timings and thresholds
| Item | Value |
|---|---|
| Damper end switch closed before PILOT IGNITION | 2 seconds |
| Damper end switch open before DAMPER FAULT | 45 seconds |
| Hold after DAMPER FAULT | 6 minutes |
| Pilot flame stability check after flame is seen | 2 seconds |
| Pilot flame sense timer before retry | 15 seconds |
| Wait before ignition retry | 6 minutes |
Codes you may see during this
DAMPER FAULT OPENING DAMPER PILOT IGNITION
Applies to: EG water boilers 30-75, natural gas
Models
EG-30 through EG-75 water boilers
More Weil-McLain boiler sequences
- Annual start-up checklist (service technician) · Startup
- Blower calibration at first startup · Startup
- Check flame and combustion with instruments · Startup
- Check flame and combustion with instruments at high fire, low fire and auto · Startup
- Closure switch interlock startup sequence · Startup
- Express Setup Example B wizard order (Combi with two zones) · Startup
- Final verification checklist at commissioning · Startup
- Lighting and operating sequence · Startup
Take it to the job
Sequences of operation, error codes and tips work offline in the HVACopedia app.
Source: EG / PEG Series 7 Boiler Manual, p. 48. Written in our own words; timings can differ by model and software version, so check the manual for your exact unit.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.