What happens, in order
- With the inducer on, the air pressure switch and high fire pressure switch are both closed.
- The air pressure switch closes the safety circuit for the Unity CI control.
- The high fire pressure switch completes the circuit to the high fire input of the gas valve, so the valve can deliver full manifold pressure.
Applies to: CGi-4, CGi-7, CGi-8
Models
CGi-4CGi-7CGi-8
More Weil-McLain boiler sequences
- Annual start-up checklist (service technician) · Startup
- Blower calibration at first startup · Startup
- Check flame and combustion with instruments · Startup
- Check flame and combustion with instruments at high fire, low fire and auto · Startup
- Closure switch (flow switch or CAD) proof sequence · Startup
- Closure switch interlock startup sequence · Startup
- Express Setup Example B wizard order (Combi with two zones) · Startup
- Final verification checklist · Startup
Take it to the job
Sequences of operation, error codes and tips work offline in the HVACopedia app.
Source: CGi Series 5 boiler manual, p. 60. Written in our own words; timings can differ by model and software version, so check the manual for your exact unit.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.