Direct exhaust sidewall termination installation sequence

Ultra Series 4

What happens, in order

  1. Install the boiler.
  2. Locate each wall penetration and prepare it before installing vent piping.
  3. Attach external pipe and fittings as the termination instructions show.
  4. Support vertical runs outside the building with brackets.
  5. Install vent piping from boiler to termination.
  6. Install a hanger within 6 inches of any upturn in the piping.
  7. Install pipe supports every 5 feet on horizontal and vertical runs.
  8. Slope horizontal piping down toward the boiler at least 1/4 inch per foot.
  9. Connect vent piping at the boiler per the vent connection instructions.

Timings and thresholds

ItemValue
Hanger support distance from any upturnwithin 6 inches
Pipe support spacingevery 5 feet
Horizontal slope toward boilerat least 1/4 inch per foot

Applies to: Direct exhaust sidewall vent

More Weil-McLain boiler sequences

Take it to the job

Sequences of operation, error codes and tips work offline in the HVACopedia app.

Open the app

Source: Ultra Series 4 boiler manual, p. 86. Written in our own words; timings can differ by model and software version, so check the manual for your exact unit.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.