Direct exhaust installation sequence
What happens, in order
- Install the boiler.
- Locate the roof or wall penetration for each termination. Prepare roof penetrations before installing vent piping.
- Attach external pipe and fittings as shown in the termination instructions. Vertical terminations use the addendum instructions.
- Support vertical runs on the outside of the building with brackets as shown in the termination instructions.
- Install vent piping from the boiler to the termination. Put a hanger within 6 in of any upturn. Slope horizontal piping down toward the boiler at least 1/4 in per foot.
- Connect the vent piping at the boiler per the manual.
Applies to: Direct exhaust installations using room combustion air
More Weil-McLain boiler sequences
- Annual start-up checklist (service technician) · Startup
- Blower calibration at first startup · Startup
- Check flame and combustion with instruments · Startup
- Check flame and combustion with instruments at high fire, low fire and auto · Startup
- Closure switch interlock startup sequence · Startup
- Express Setup Example B wizard order (Combi with two zones) · Startup
- Final verification checklist at commissioning · Startup
- Lighting and operating sequence · Startup
Take it to the job
Sequences of operation, error codes and tips work offline in the HVACopedia app.
Source: Weil-McLain Ultra Series 4 boiler manual, p. 26. Written in our own words; timings can differ by model and software version, so check the manual for your exact unit.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.