Weil-McLain · Boiler · Standby/shutdown

Demand satisfied, postpurge and interpurge

ECO Tec Series 3

What happens, in order

  1. When the demand is met (target temperature or limit reached), the gas valve closes.
  2. The blower runs postpurge at ignition speed, then the boiler returns to standby.
  3. Between failed ignitions, the blower runs at purge speed to clear exhaust before the next try.

Applies to: ECO Tec Series 3

More Weil-McLain boiler sequences

Take it to the job

Sequences of operation, error codes and tips work offline in the HVACopedia app.

Open the app

Source: ECO Tec Series 3 Condensing Gas Boiler Boiler Manual, p. 84. Written in our own words; timings can differ by model and software version, so check the manual for your exact unit.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.