Control sequence of operation (call for heat to modulation)
What happens, in order
- Power up the screen lists detected sensors; confirm the model and that all sensors show.
- Standby no call for heat; the display cycles dots and shows a wrench if maintenance is due.
- Blower on call for heat detected; start circulators for the priority; calculate target; if sensor temp is below target, begin firing.
- Wait for the closure switch, if used; blower goes to purge speed for prepurge; check min air flow switch.
- Ignition after prepurge, go to ignition speed; open gas valve and spark; spark stops and the flame rod checks for flame.
- Space heating or DHW heating once flame is detected, release to modulation; switch priority when the priority timer ends.
- Blower off demand satisfied; close gas valve; blower runs ignition speed for postpurge; return to standby.
- If no flame is detected, the gas valve closes, postpurge runs and the cycle restarts. After 2 failures the control locks out.
- Maintenance the display turns blue during standby when the maintenance timer expires; the boiler still runs.
- Error or fault display turns red; a flashing display means lockout.
- WWSD space heating is blocked when outdoor temperature is above the WWSD setting; DHW is not affected.
Timings and thresholds
| Item | Value |
|---|---|
| Closure switch proof window | 4 minutes |
| Flame failure retries before lockout | 2 failures |
Applies to: SF1000L/R, SF1500L/R, SF2000L/R
Models
SF1000SF1500SF2000
More Weil-McLain boiler sequences
- Annual start-up checklist (service technician) · Startup
- Blower calibration at first startup · Startup
- Check flame and combustion with instruments · Startup
- Check flame and combustion with instruments at high fire, low fire and auto · Startup
- Closure switch (flow switch or CAD) proof sequence · Startup
- Closure switch interlock startup sequence · Startup
- Express Setup Example B wizard order (Combi with two zones) · Startup
- Final verification checklist · Startup
Take it to the job
Sequences of operation, error codes and tips work offline in the HVACopedia app.
Source: SlimFit Series 2 Boiler Manual 550-100-561/1225, p. 62. Written in our own words; timings can differ by model and software version, so check the manual for your exact unit.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.