Central heat call with residual heat recovery and delayed ignition
What happens, in order
- Thermostat calls for heat and the circulator starts.
- Control measures how the boiler water temperature changes.
- Control calculates a delay based on these readings.
- Burner only fires after the control decides residual hot water cannot satisfy the demand.
- ECONOMY SETTING sets how long the residual heat attempt may run.
Timings and thresholds
| Item | Value |
|---|---|
| Minimum delay (ECONOMY SETTING 10%) | Gas enabled immediately |
| Maximum delay (ECONOMY SETTING 100%) | Up to 120 seconds |
Applies to: CGi Series 5 all models
More Weil-McLain boiler sequences
- Annual start-up checklist (service technician) · Startup
- Blower calibration at first startup · Startup
- Check flame and combustion with instruments · Startup
- Check flame and combustion with instruments at high fire, low fire and auto · Startup
- Closure switch (flow switch or CAD) proof sequence · Startup
- Closure switch interlock startup sequence · Startup
- Express Setup Example B wizard order (Combi with two zones) · Startup
- Final verification checklist · Startup
Take it to the job
Sequences of operation, error codes and tips work offline in the HVACopedia app.
Source: Weil-McLain CGi Series 5 boiler manual, p. 51, 55. Written in our own words; timings can differ by model and software version, so check the manual for your exact unit.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.