Call for heat with residual-heat delay
What happens, in order
- Central heat call starts and the circulator is energized.
- The control circulates the water already in the system and measures how the boiler water temperature changes.
- The control calculates a delay from those measurements.
- If the hot water in the system cannot satisfy the demand, the boiler is turned on after the delay.
- The ECONOMY ADJUST setting scales the delay; at 10% the delay is the shortest possible.
Timings and thresholds
| Item | Value |
|---|---|
| Economy setting at minimum (10%) | Gas heat enabled immediately when the thermostat demand starts |
| Economy setting at maximum (100%) | Gas heat enable may be delayed up to 120 seconds |
Applies to: CH call with economy setting; not used when ODR is enabled
More Weil-McLain boiler sequences
- Annual start-up checklist (service technician) · Startup
- Blower calibration at first startup · Startup
- Check flame and combustion with instruments · Startup
- Check flame and combustion with instruments at high fire, low fire and auto · Startup
- Closure switch (flow switch or CAD) proof sequence · Startup
- Closure switch interlock startup sequence · Startup
- Express Setup Example B wizard order (Combi with two zones) · Startup
- Final verification checklist · Startup
Take it to the job
Sequences of operation, error codes and tips work offline in the HVACopedia app.
Source: CGi Series 5 Gas-Fired Water Boiler Boiler Manual, p. 51, 55. Written in our own words; timings can differ by model and software version, so check the manual for your exact unit.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.