What happens, in order
- Check the heating system pressure on the pressure gauge.
- Open the oil shut-off valves at the tank and filter, or open the gas shut-off valve, whichever applies.
- Switch on the power supply, for example at the separate fuse or disconnect switch.
- Switch on the on/off switch; the green status lamp lights and the boiler temperature appears in the display after a short time.
- The system and any remote controls are now ready for operation.
Timings and thresholds
| Item | Value |
|---|---|
| Boiler temperature shown in display | after a short time |
Applies to: Vitotronic 300 Model GW2
Models
Vitotronic 300 Model GW2
More Viessmann boiler sequences
- AUX output as combustion air function · Startup
- Boiler startup protection · Startup
- Commissioning assistant at first start-up · Startup
- Control commissioning start-up · Startup
- Initial start-up preparation · Startup
- Initial start-up sequence after installation · Startup
- Lighting and operating instructions · Startup
- Matching the control unit to a modulating burner · Startup
Take it to the job
Sequences of operation, error codes and tips work offline in the HVACopedia app.
Source: Vitotronic 300 GW2 operating instructions, p. 11. Written in our own words; timings can differ by model and software version, so check the manual for your exact unit.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.