Viessmann · Boiler · Startup
Commissioning assistant at first start-up
What happens, in order
- Turn ON the ON/OFF switch on all control units. The commissioning assistant starts automatically.
- Set Language, Date / Time and Temperature units.
- Tap Application and select single boiler, lead boiler and cascade, or lag boiler.
- Confirm with OK until the symbol and Setup appear.
- Tap Yes to set the important coding during commissioning, or No if no further settings are needed.
- Confirm with OK. A single boiler shows the standard menu; a multi boiler system shows the default display.
- If commissioning fails, a fault symbol appears in the footer. Tap it and check the fault messages.
Applies to: Vitotronic 300 GW6B, all applications
More Viessmann boiler sequences
- AUX output as combustion air function · Startup
- Boiler startup protection · Startup
- Control commissioning start-up · Startup
- Initial start-up preparation · Startup
- Initial start-up sequence after installation · Startup
- Lighting and operating instructions · Startup
- Matching the control unit to a modulating burner · Startup
- Matching the control unit to a two-stage burner · Startup
Take it to the job
Sequences of operation, error codes and tips work offline in the HVACopedia app.
Source: Vitotronic 300 GW6B installation and service manual, p. 48. Written in our own words; timings can differ by model and software version, so check the manual for your exact unit.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.