What happens, in order
- Enter the Slab curing prog level and select a day.
- Press F [OK] to activate the day, set the flow temperature, then press F [OK] to save.
- Repeat for each required day; enter '----' to end the program.
- Turn Slab curing to On to start the program.
- Controller holds the set flow temperature for each day at 00:00; the mixing valve circuits control to it while the boiler supplies it regardless of operating mode.
- After the program ends, the controller goes back to the selected operating mode.
Timings and thresholds
| Item | Value |
|---|---|
| Program duration | maximum 28 days |
| Day change | 00:00 hrs |
| Setpoint range per day | 10°C to 60°C |
Applies to: Versatronik 200 screed drying
More Viessmann boiler sequences
- AUX output as combustion air function · Startup
- Boiler startup protection · Startup
- Commissioning assistant at first start-up · Startup
- Control commissioning start-up · Startup
- Initial start-up preparation · Startup
- Initial start-up sequence after installation · Startup
- Lighting and operating instructions · Startup
- Matching the control unit to a modulating burner · Startup
Take it to the job
Sequences of operation, error codes and tips work offline in the HVACopedia app.
Source: Versatronik 200 installation and operating manual, p. 148. Written in our own words; timings can differ by model and software version, so check the manual for your exact unit.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.