Viessmann · Boiler · Standby/shutdown
Shutting down the heating system
What happens, in order
- For temporary non-use, switch to standby using the heating program selection instead of full shutdown.
- For long periods (several months), switch off the on/off switch.
- Close the oil shut-off valves at the tank and filter, or close the gas shut-off valve, whichever applies.
- Switch off the power supply, for example at the separate fuse or disconnect switch.
- Contact the heating contractor before and after a long shutdown for freeze-up protection and heat exchanger protection.
Applies to: Vitotronic 300 Model GW2
Models
Vitotronic 300 Model GW2
More Viessmann boiler sequences
- AUX output as combustion air function · Startup
- Boiler startup protection · Startup
- Commissioning assistant at first start-up · Startup
- Control commissioning start-up · Startup
- Initial start-up preparation · Startup
- Initial start-up sequence after installation · Startup
- Lighting and operating instructions · Startup
- Matching the control unit to a modulating burner · Startup
Take it to the job
Sequences of operation, error codes and tips work offline in the HVACopedia app.
Source: Vitotronic 300 GW2 operating instructions, p. 11. Written in our own words; timings can differ by model and software version, so check the manual for your exact unit.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.