Burner shutdown, gas valve proof of closure and post-purge
What happens, in order
- Phase 7 after any normal or uncontrolled shutdown, the flame safeguard runs a full mechanical and electrical gas valve proof of closure test.
- After a successful test, the flame must not be present. If flame existed for more than 15 seconds, the flame safeguard locks out permanently.
- Phase 8 both gas valves close and post-purge speed test runs; call for heat ends.
- Phase 9 if the fixed high limit trips in normal operation, the blower purges for 15 minutes to cool the heat exchanger.
Timings and thresholds
| Item | Value |
|---|---|
| Flame present after shutdown before permanent lockout | more than 15 seconds |
| High limit post-purge | 15 minutes |
Applies to: Burner shutdown
Models
B2HB 45B2HB 57B2HB 160B2HB 199
More Viessmann boiler sequences
- AUX output as combustion air function · Startup
- Boiler startup protection · Startup
- Commissioning assistant at first start-up · Startup
- Control commissioning start-up · Startup
- Initial start-up preparation · Startup
- Initial start-up sequence after installation · Startup
- Lighting and operating instructions · Startup
- Matching the control unit to a modulating burner · Startup
Take it to the job
Sequences of operation, error codes and tips work offline in the HVACopedia app.
Source: Vitodens 200-W B2HB service manual, p. 93. Written in our own words; timings can differ by model and software version, so check the manual for your exact unit.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.