Fill and deaerate the boiler during commissioning

I-Series Plus

What happens, in order

  1. Confirm all boiler components are installed correctly.
  2. Open the air vent inside the boiler.
  3. Confirm all heat emitters and pumps are connected to the piping.
  4. Power on the boiler. The fan runs for a safety check.
  5. Open the fill valve and fill the boiler to 20-30 PSI (138-207 kPa).
  6. Check the heating system for leaks.
  7. Start deaeration (press and hold SW2 on the PC board).
  8. Let deaeration run until the display shows End.
  9. Press the top left black button on the PC board to return to normal operation.
  10. Run DHW or CH to confirm normal operation.
  11. Close the air vent on the pump. Air should be removed through the air separator within about a week.

Timings and thresholds

ItemValue
Deaeration run timeAbout 15 minutes, until the display shows End
Air removal from systemUp to one week

Codes you may see during this

E430

Applies to: I-Series Plus IP060160C

More Rinnai boiler sequences

Take it to the job

Sequences of operation, error codes and tips work offline in the HVACopedia app.

Open the app

Source: Rinnai I-Series Plus IP060160C installation and operation manual, p. 68-69. Written in our own words; timings can differ by model and software version, so check the manual for your exact unit.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.