NTI · Boiler · Standby/shutdown

Normal shutdown

TRX150

What happens, in order

  1. Turn the boiler off at the ON/OFF power switch.
  2. Wait for the combustion blower to stop so latent combustion gases are purged.

Timings and thresholds

ItemValue
Combustion blower run-down after power offmaximum 5 minutes

Applies to: TRX150

More NTI boiler sequences

Take it to the job

Sequences of operation, error codes and tips work offline in the HVACopedia app.

Open the app

Source: NTI TRX150 manual, p. 97. Written in our own words; timings can differ by model and software version, so check the manual for your exact unit.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.