Daikin · Heat pump · Pump/purge

Triple evacuation method (recommended)

DX6VSDZ6VSDZ6VSA

What happens, in order

  1. Evacuate the system to 4000 microns and hold for 15 minutes.
  2. Break the vacuum with dry nitrogen and raise system pressure to 2-3 PSIG; hold for 20 minutes.
  3. Release the nitrogen.
  4. Evacuate to 1500 microns and hold for 20 minutes.
  5. Break the vacuum again with dry nitrogen and raise pressure to 2-3 PSIG; hold for 20 minutes.
  6. Evacuate until below 500 microns and hold for 60 minutes.

Timings and thresholds

ItemValue
Evacuate to 4000 microns hold15 minutes
Nitrogen pressure hold (first)20 minutes at 2-3 PSIG
Evacuate to 1500 microns hold20 minutes
Nitrogen pressure hold (second)20 minutes at 2-3 PSIG
Final evacuation below 500 microns hold60 minutes

Applies to: Refrigerant side evacuation

Models

DX6VSDZ6VSDZ6VSA

More Daikin heat pump sequences

Take it to the job

Sequences of operation, error codes and tips work offline in the HVACopedia app.

Open the app

Source: Daikin DX6VS/DZ6VS installation manual (3P731493-1), p. 19. Written in our own words; timings can differ by model and software version, so check the manual for your exact unit.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.