System start-up procedure with evacuation and checks
What happens, in order
- Confirm the factory refrigerant charge matches the indoor unit and line set. Add charge on the liquid line if the line set is longer than factory length.
- Connect high voltage power at least 2 hours before start-up.
- Do not overcharge the system and do not run the unit in a vacuum or at negative pressure.
- Use only refrigerant certified to AHRI standards. Used refrigerant can damage the compressor.
- Keep the liquid and suction valves closed until the indoor unit and line set are evacuated.
- Connect a vacuum pump with 250 micron capability to the service valves.
- Evacuate to 500 microns or less using both the suction and liquid service valves.
- Close the pump valve and hold vacuum for 10 minutes.
- If pressure stays at or below 500 microns and steady, the system is leak-free; proceed to start-up.
- If pressure rises above 500 microns, moisture or non-condensibles may be present or there may be a leak. Recheck for leaks, repair, and evacuate again.
- Open the stop valves only after evacuation is complete.
Timings and thresholds
| Item | Value |
|---|---|
| High voltage power connected before start-up | at least 2 hours |
| Evacuation target (single method) | 500 microns or less |
| Vacuum hold check | 10 minutes |
Applies to: Outdoor units at system start-up
Models
DX6VSDZ6VSDZ6VSA
More Daikin heat pump sequences
- 3-minute standby before restart · Startup
- Commissioning and test run · Startup
- Five-step commissioning set-up · Startup
- Preheating control before inverter start (open phase) · Startup
- Triple evacuation method (recommended) · Pump/purge
- 3-D airflow auto-swing order · Other
- Commissioning sequence in the app · Other
- Compressor frequency control priority · Other
Related
Take it to the job
Sequences of operation, error codes and tips work offline in the HVACopedia app.
Source: Daikin DX6VS/DZ6VS installation manual (3P731493-1), p. 18. Written in our own words; timings can differ by model and software version, so check the manual for your exact unit.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.