Daikin · Heat pump · Startup

Commissioning and test run

Mega-Q

What happens, in order

  1. Complete the checklist before commissioning. Confirm installation, field wiring, power voltage, grounding, insulation, fuses, pipe sizes, open stop valves, no damage, no leaks, clear air inlets and outlets, water circuit filled and required water flow.
  2. Turn on power to the hot water generation system and tank control board.
  3. Set the address on each cascade unit.
  4. Release air from the cascade unit water piping.
  5. Run the cascade unit pump from the remote controller to purge air from the piping between the cascade unit and the hot water storage tank.
  6. Perform the test operation of the hot water generation system.
  7. If the test run ends abnormally, correct the errors and repeat.
  8. Hand over the system for operation.

Timings and thresholds

ItemValue
Power on before operation to energize the crankcase heater6 hours
Compressor run-in before stable power use50 hours of continuous run time

Codes you may see during this

UC

Applies to: Mega-Q heat source, cascade and tank control board

Models

RXHWQ120MQTJABWLP120TJU

More Daikin heat pump sequences

Take it to the job

Sequences of operation, error codes and tips work offline in the HVACopedia app.

Open the app

Source: Mega-Q installation manual, p. 33-35. Written in our own words; timings can differ by model and software version, so check the manual for your exact unit.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.