Vent checks for the furnace exhaust and intake piping.

Check in this order

  1. Confirm the vent is 2 in or 3 in schedule 40 PVC, CPVC, polypropylene, or Type BH special gas vent (ULC-S636) for Category IV in Canada, following local codes and the manual.
  2. Confirm ABS or PVC cellular core pipe is not used for venting.
  3. Slope the vent upward toward the termination at 1/4 in per foot (2% grade).
  4. Support all vent runs and the vent termination.
  5. Seal the air intake and exhaust connections on the flue and vent lines.
  6. Install termination screen caps on the exhaust and intake pipes.
  7. Check the venting for leaks.
  8. Confirm the vent termination is at least 12 in (300 mm) above exterior grade.
  9. Confirm make-up air is sufficient.
  10. Confirm total vent length is within the maximum allowed.

Applies to: NPF700 series (all listed models)

More furnace guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: Navien NPF installation and operation manual, p. 93. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.