Confirm before commissioning that the location and gas supply are correct. Each item must be a yes before the install is complete.

Check in this order

  1. Confirm required clearances from building openings and intake vents, and keep the vent termination as close to the furnace as practical.
  2. Confirm service clearances, make-up air and that the area is free of dust, corrosive elements and flammable vapors.
  3. Confirm the furnace and vent piping are clear of combustibles such as clothing, cleaning materials and rags.
  4. Install the pressure relief valve. If auto water fill is not used, fill the water tank manually. If auto fill is used, confirm the water line is installed.
  5. Confirm the gas supply type matches the rating plate.
  6. Confirm the gas line is at least 1/2 in or 3/4 in ID and is long and large enough to deliver the required BTU load.
  7. Measure the gas supply line pressure and confirm it is inside the range in the manual.
  8. Confirm a manual gas shut-off valve is installed.
  9. Pressure-test the gas line and all fittings for leaks.
  10. Confirm the gas company has inspected the installation if required.

Applies to: NPF700 series (all listed models)

More furnace guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: Navien NPF installation and operation manual, p. 92. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.