Navien · Furnace troubleshooting

Gas regulator arrangements for LP supply

NPF

What is going on

The manual shows a single regulator system (12 in WC) and a two stage system with a high pressure and a low pressure regulator. The two stage system is recommended.

Likely causes

  • Supply pressure or tank arrangement does not suit a single regulator

Check in this order

  1. Use the single regulator (12 in WC) layout only where it suits the site.
  2. Prefer the two stage layout a high pressure regulator at the tank feeding a low pressure regulator that goes to the building.
  3. Keep full size gas pipe run to the appliance.
  4. Check the excess flow valve rating before installing one (see the EFV tip).

Applies to: NPF700 series on LP gas

More furnace guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: Navien NPF installation and operation manual, p. 47. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.