Navien · Furnace troubleshooting

Furnace power connection and grounding

NDF

What is going on

The junction box is in the blower compartment. Connect the house wiring to the furnace leads, and make sure the cabinet is continuously grounded.

Check in this order

  1. Shut off power at the fuse box or service panel before connecting.
  2. Connect the black wire to L1 (hot).
  3. Connect the white wire to L2 (neutral).
  4. Connect the green wire to ground in the junction box.
  5. Use copper conductors only and quality wire nuts.
  6. Do not use gas piping as a ground.
  7. To move the junction box to the other side, fasten it to the chosen side panel, use only ground screws for the enclosure, and fit the plastic cap to the unused panel.

Applies to: Furnace line voltage wiring

More furnace guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: Navien NDF installation and operation manual, p. 53 to 54. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.