Ductwork layout and return air connection for upflow, horizontal and downflow orientations.
Check in this order
- Position the furnace to keep ductwork short and minimise fittings.
- Cut the return air opening the full width of the return air markers on the side panel. Choose bottom, either side, or a combination.
- For upflow, the return duct may connect to either side or the bottom opening.
- For horizontal and downflow, connect the return duct to the designated return opening opposite the supply outlet.
- Do not use the rear panel as a return air inlet.
- Connect the return air duct or filter fitting airtight so combustion gases from nearby appliances cannot be drawn in.
- Leave enough space and access to remove the air filter.
- If an A/C evaporator coil is used, install it on the supply side and make sure no air bypasses it. Never install the furnace downstream of the coil.
- Connect the supply air plenum to the supply outlet. Use flexible connectors where needed and support the adjoining duct independently.
Applies to: NDF600 series furnaces
More furnace guides
Take it to the job
All guides, error codes and tips work offline in the HVACopedia app.
Source: Navien NDF Forced Air Gas Furnace Installation and Operation Manual, p. 18. Written in our own words; check the manual for your exact model.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.