What is going on

Example layout with up to three zones, each on its own pump, with a common air separator, expansion tank, pressure relief valve, pressure reducing valve, backflow preventer and make-up water.

Check in this order

  1. Install a NaviClean filter in the system return to remove debris.
  2. Use a pump with an integral check valve, or fit a check valve at the pump outlet.
  3. Make make-up water connections per section 11.1 (p. 110) and local code.
  4. Wire the zone pumps per section 3.6.3 (p. 40).

Applies to: NCB700 zone pump system

More boiler guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: Navien NCB700 installation and operation manual, p. 31. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.