Navien · Boiler troubleshooting

Accessing the control board terminals

NCB700

What is going on

The control board (PCB) terminals are behind the front cover. Electrical shock can cause serious injury or death, so disconnect power before any work inside the boiler.

Check in this order

  1. Turn off power to the boiler at the supply.
  2. With a Phillips screwdriver, remove the 4 front-cover screws (2 top and 2 bottom).
  3. Work on the terminal blocks only after confirming power is off.
  4. Label all wires before disconnecting any control wiring.
  5. Check normal operation of the boiler after any service.

Applies to: NCB700 control board access

More boiler guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: Navien NCB700 installation and operation manual, p. 207. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.