Wall mounting the boiler
What is going on
Mount the upper bracket on studs, then hang the boiler and secure the bottom.
Check in this order
- Drill into studs and into drywall for plastic anchors; the bracket is pre-drilled at 16 in on center.
- Reinforce the wall if it is weak or framing is uneven.
- Fix the bracket level and confirm it can carry the boiler weight.
- Start one screw, check level, then install the other three.
- With help, lift the boiler above the bracket hooks and lower it onto them. Mounted this way, the back sits 5/8 in from the wall.
- Install two screws through the bottom bracket to secure the boiler.
- Leave clearance for service access.
Applies to: All NCB700 models
More boiler guides
Take it to the job
All guides, error codes and tips work offline in the HVACopedia app.
Source: Navien NCB700 installation and operation manual, p. 16. Written in our own words; check the manual for your exact model.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.