Full-port ball valves are required. Check valves are recommended but must not sit between the close-spaced T connections and the expansion tank.

Check in this order

  1. Use full-port ball valves on the heating circuit
  2. Install check valves to prevent reverse flow during off-cycle pumping
  3. Do not install check valves, motorized valves or other shutoffs between the close T connections and the expansion tank, except for service
  4. Use unions to make service easier
  5. Tighten service valves carefully to avoid damaging them

Applies to: NCB700 space heating system

More boiler guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: Navien NCB700 installation and operation manual, p. 187. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.