Navien · Boiler troubleshooting

Installing the condensate siphon loop on a cascade system

NCB700

What is going on

The condensate drain forms a siphon loop that must be primed with water before the boiler runs.

Check in this order

  1. Form a loop in the field-supplied drain hose and secure it with a tie. Do not kink the hose or tie it too tight.
  2. Prime the loop with tap water. Water in the hose must be above 7.9 in (200 mm) and must be present before the boiler runs.
  3. Connect the hose to the cascade system and route the end to a drain.
  4. Check that the loop still holds water before each operation.

Applies to: NCB700-190/060, NCB700-190/080, NCB700-240/110, NCB700-240/130, NCB700-250/150

More boiler guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: Navien NCB700 installation and operation manual, p. 103. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.