What is going on

Mount the manifold between the boiler's heating connections and the system piping, with the boiler already mounted on the wall.

Check in this order

  1. Shut off the water supply to the site and confirm the boiler is mounted per the boiler installation manual.
  2. Check that the manifold kit and valve kit contain the pipe, unions, gaskets and valves.
  3. Apply thread sealant to the 1" heating SUPPLY and RETURN fittings at the bottom of the boiler.
  4. Identify the red SUPPLY and blue RETURN connections on the manifold.
  5. Connect the manifold to the boiler's supply and return fittings using the 1" unions supplied with the manifold.
  6. Seal all water connections tightly to prevent leaks.
  7. Attach the system supply and return piping to the 1-1/4" main pipe ends on the manifold and support the plumbing weight.
  8. Check all unions, gaskets and fittings are sealed before initial operation.

Applies to: NCB-H and NFC Series Navien combi-boilers with the primary manifold accessory

More boiler guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: Navien NCB-H, NFC Series Primary Manifold installation instructions, p. 1-2. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.