Install the heating system relief valve
What is going on
Install the relief valve vertically on the boiler outlet through the universal adapter, with a vent on the adapter. The valve must be ASME approved.
Check in this order
- Connect the universal adapter to the RAL adapter on top of the boiler
- Install the relief valve and a vent on the universal adapter
- Check that the relief valve capacity is at least the maximum heating system pressure
- Check that the valve's BTU/H rating is at least the boiler's maximum input
- Run the discharge pipe so hot water cannot spray the operator or equipment
- Terminate the discharge pipe 50 to 150 mm (2 to 6 in) above the floor or floor drain so the discharge is visible
- Keep the discharge pipe free of valves, reducers and blockages
- Do not install any other valve between the relief valve and the boiler
- After filling and pressurizing, test the valve by lifting the lever; replace the valve right away if it does not work
- Test the valve manually at least once a year
Applies to: NCB700 space heating system
More boiler guides
Take it to the job
All guides, error codes and tips work offline in the HVACopedia app.
Source: Navien NCB700 installation and operation manual, p. 184-185. Written in our own words; check the manual for your exact model.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.