Gas supply sizing and piping
What is going on
Gas meter capacity must cover all connected appliances. The boiler should be the first appliance on the gas line.
Check in this order
- Confirm the gas meter capacity exceeds the total connected load (boiler plus furnace plus other appliances). Example in manual: 425 CFH meter for 195 + 58.8 + 63.7 CFH loads.
- Use 3/4 in rigid pipe sized per the Installation & Operation Manual tables.
- Do not use 3/4 in corrugated connectors or tubing, as they can cause noise.
- Leak test the appliance and gas connection before operation.
Applies to: NFB-301C/399C
More boiler guides
Take it to the job
All guides, error codes and tips work offline in the HVACopedia app.
Source: Navien NFB-C quick installation guide, p. 1-2. Written in our own words; check the manual for your exact model.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.