Fixing the frame to the location

Ready-Link Commercial

What is going on

Secures the rack to the floor before the boiler is hung.

Check in this order

  1. Check that all screws and bolts are tight.
  2. Fix the frame to the floor with anchor bolts (3/8 in) that stick up at least 2 in (50 mm) above the floor.
  3. Confirm the floor is flat and strong enough for the boiler and frame.

Applies to: Ready-Link Commercial rack, floor fixing

More boiler guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: Ready-Link Commercial Rack System installation guide, p. 2. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.