Fixing the frame to the location
What is going on
Secures the rack to the floor before the boiler is hung.
Check in this order
- Check that all screws and bolts are tight.
- Fix the frame to the floor with anchor bolts (3/8 in) that stick up at least 2 in (50 mm) above the floor.
- Confirm the floor is flat and strong enough for the boiler and frame.
Applies to: Ready-Link Commercial rack, floor fixing
More boiler guides
Take it to the job
All guides, error codes and tips work offline in the HVACopedia app.
Source: Ready-Link Commercial Rack System installation guide, p. 2. Written in our own words; check the manual for your exact model.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.