Typical wiring for a terminal-type low water cutoff (LWCO) where the boiler supplies 24 VAC to the LWCO power terminals.
Check in this order
- Turn off the power to the boiler before working on the terminal strips.
- The boiler supplies 24 VAC at the LWCO power terminals (CNC3).
- Connect the LWCO to the boiler LWCO terminals.
- Use a jumper between the LWCO and the neutral as shown in the wiring diagram, with the same voltage for control and burner circuit.
- Verify proper operation after servicing.
Applies to: NCB700 with external LWCO
More boiler guides
Take it to the job
All guides, error codes and tips work offline in the HVACopedia app.
Source: Navien NCB700 installation and operation manual, p. 39. Written in our own words; check the manual for your exact model.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.