Navien · Boiler troubleshooting

External low water cutoff (LWCO) installation

NCB700

What is going on

A separate external LWCO is needed only if local code requires it. The internal device is factory installed.

Check in this order

  1. Check local code to see whether an external LWCO is required
  2. Install the external LWCO at least 152 mm (6 in) above the top of the heat exchanger
  3. Wire the LWCO to the boiler control board using the generic wiring diagram
  4. Inspect and service the external LWCO annually per its instructions

Applies to: NCB700 space heating system

More boiler guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: Navien NCB700 installation and operation manual, p. 185-186. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.