A separate external LWCO is needed only if local code requires it. The internal device is factory installed.
Check in this order
- Check local code to see whether an external LWCO is required
- Install the external LWCO at least 152 mm (6 in) above the top of the heat exchanger
- Wire the LWCO to the boiler control board using the generic wiring diagram
- Inspect and service the external LWCO annually per its instructions
Applies to: NCB700 space heating system
More boiler guides
Take it to the job
All guides, error codes and tips work offline in the HVACopedia app.
Source: Navien NCB700 installation and operation manual, p. 185-186. Written in our own words; check the manual for your exact model.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.