Navien · Boiler troubleshooting
Electrical connections
What is going on
Power and external control connections on the main PCB.
Check in this order
- Disconnect power before making any wire connections on the main PCB.
- Supply 120 V AC, 60 Hz, minimum 2 A, with proper grounding.
- Wire the external LWCO if required by local codes; confirm the built-in device meets code.
- Do not operate with abnormally high or low AC voltage.
Applies to: NFB-301C/399C
More boiler guides
Take it to the job
All guides, error codes and tips work offline in the HVACopedia app.
Source: Navien NFB-C quick installation guide, p. 3. Written in our own words; check the manual for your exact model.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.