Navien · Boiler troubleshooting

Connecting the vent pipe to the vent collar

NCB700

What is going on

Correct insertion and clamping of the exhaust pipe onto the boiler collar.

Check in this order

  1. Cut the vent pipe square (90°) and deburr it.
  2. Lubricate the pipe end with water only. Do not use grease, primer or cement on the appliance connection.
  3. Mark the pipe 2-3/4 in (70 mm) from its end.
  4. Start the run with straight pipe. Do not use a street elbow at the collar.
  5. Push the pipe in with a twisting motion until it bottoms in the collar, leaving the mark hidden.
  6. Tighten the clamp with an 8 mm socket.
  7. Turn on the boiler and bubble-test all exhaust joints for gas leaks.

Applies to: NCB700 series

More boiler guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: Navien NCB700 installation and operation manual, p. 61-62. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.