What is going on

Connect the cascade units with Ready-Link cables. All units must be powered off before connecting.

Check in this order

  1. Make sure power is off to all units.
  2. Connect the Ready-Link cables to the CNK1 terminal strip on the NCB700.
  3. Connect the Ready-Link cables to the J6 ports on the left side of the front panel of each NPE-A2 water heater.
  4. Restore power to the boiler and turn all boilers on with the Power button.

Applies to: NCB700 cascade with NPE-A2 or NPE-S2 water heaters

More boiler guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: Navien NCB700 installation and operation manual, p. 87. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.